[ARCHIVED] Waterway Village Pedestrian Bridge Progress Update

Ped Bridge Update 2-27

The skyline over the Intracoastal is changing every day! Work on the Waterway Village Pedestrian Bridge is charging ahead as we reach new milestones in connecting our community.


๐—ฃ๐—ฟ๐—ผ๐—ท๐—ฒ๐—ฐ๐˜ ๐—ฆ๐—ป๐—ฎ๐—ฝ๐˜€๐—ต๐—ผ๐˜ (๐—ฎ๐˜€ ๐—ผ๐—ณ ๐—™๐—ฒ๐—ฏ๐—ฟ๐˜‚๐—ฎ๐—ฟ๐˜† ๐Ÿฎ๐Ÿณ, ๐Ÿฎ๐Ÿฌ๐Ÿฎ๐Ÿฒ):


• ๐—ฆ๐˜๐—ฎ๐˜๐˜‚๐˜€: On Schedule โœ…

• ๐—ง๐—ถ๐—บ๐—ฒ ๐—˜๐—น๐—ฎ๐—ฝ๐˜€๐—ฒ๐—ฑ: 355 days (52.6% of schedule)

• ๐—”๐—ป๐˜๐—ถ๐—ฐ๐—ถ๐—ฝ๐—ฎ๐˜๐—ฒ๐—ฑ ๐—–๐—ผ๐—บ๐—ฝ๐—น๐—ฒ๐˜๐—ถ๐—ผ๐—ป: January 8, 2027


๐—–๐˜‚๐—ฟ๐—ฟ๐—ฒ๐—ป๐˜ ๐—ช๐—ผ๐—ฟ๐—ธ:

๐—ฅ๐—ผ๐—ฎ๐—ฑ๐˜„๐—ฎ๐˜† & ๐—ฆ๐—ถ๐—ฑ๐—ฒ๐˜„๐—ฎ๐—น๐—ธ๐˜€: Concrete and roadway teams have been busy on ALT 1, pouring sidewalks, ribbon curbs, and laying brick pavers. Permanent striping was applied this Wednesday to prepare for the reopening of E 2nd Street!


๐—•๐—ฟ๐—ถ๐—ฑ๐—ด๐—ฒ & ๐—˜๐—น๐—ฒ๐˜ƒ๐—ฎ๐˜๐—ผ๐—ฟ ๐—ง๐—ผ๐˜„๐—ฒ๐—ฟ๐˜€:

• ๐—ก๐—ผ๐—ฟ๐˜๐—ต ๐—ฆ๐—ถ๐—ฑ๐—ฒ: The North Bridge Pile Cap is curing and being backfilled. Meanwhile, the North Elevator Tower pile cap was poured last week and is also being prepped for vertical wall construction.

• ๐—ฆ๐—ผ๐˜‚๐˜๐—ต ๐—ฆ๐—ถ๐—ฑ๐—ฒ: A major milestone this week with the concrete pour for the South Elevator Tower roof slab on Thursday! Crews also poured the 2nd vertical section of the bridge columns on Monday.


๐—ง๐—ฟ๐—ฎ๐—ณ๐—ณ๐—ถ๐—ฐ & ๐—ฆ๐—ฎ๐—ณ๐—ฒ๐˜๐˜†:

• ๐—ฅ๐—ผ๐—ฎ๐—ฑ ๐—ฅ๐—ฒ๐—ผ๐—ฝ๐—ฒ๐—ป๐—ถ๐—ป๐—ด: ALT 1 is planned to open to normal traffic operations by COB this Sunday, March 1st.

• ๐—Ÿ๐—ผ๐—ฐ๐—ฎ๐—น ๐—”๐—ฐ๐—ฐ๐—ฒ๐˜€๐˜€: Please note that parking along ALT 1 may still be restricted for finish work, and access north of the ICW remains for local traffic only during ALT 2 construction.


๐—Ÿ๐—ผ๐—ผ๐—ธ ๐—”๐—ต๐—ฒ๐—ฎ๐—ฑ:

Keep an eye out for these next steps:

• ๐—ฅ๐—ผ๐—ฎ๐—ฑ๐˜„๐—ฎ๐˜† teams will finalize ALT 1 work and shift focus to ALT 2 entrances and sidewalks.

• ๐—ฆ๐˜๐—ฟ๐˜‚๐—ฐ๐˜๐˜‚๐—ฟ๐—ฒ๐˜€ team will begin the third vertical section of the South Bridge Bent Columns.

• ๐— ๐—ถ๐—ฑ-๐— ๐—ฎ๐—ฟ๐—ฐ๐—ต ๐—ž๐—ถ๐—ฐ๐—ธ๐—ผ๐—ณ๐—ณ:Construction is scheduled to begin on the North Bridge Columns and North Elevator Tower Walls!


Thank you for your continued patience as we build this landmark for Gulf Shores!GS Ped Bridge NEWGS Ped Bridge NEW 4

GS Ped Bridge NEW 2GS Ped Bridge NEW 3

Facebook Twitter Email

Other News in Latest News

Spring Market 2025

Spring Market 2026 Coming Soon!

Posted on: March 11, 2026
West Beach Blvd

TAP Grant Bringing Pedestrian Safety Improvements to W Beach Blvd!

Posted on: March 9, 2026 | Last Modified on: March 9, 2026
Gulf Shores Special Olympian Leighann Landrum

Cheering on Our Special Olympians!

Posted on: March 3, 2026
Arbor Day

Gulf Shores Community Unites to Celebrate Arbor Day!

Posted on: February 24, 2026 | Last Modified on: March 11, 2026
GCAA Tile

2025 Nonprofit Grant Recipient Spotlight: Gulf Coast Arts Alliance

Posted on: February 3, 2026 | Last Modified on: February 3, 2026
Copy of Special Recycling Days

Special Recycling Drive

Posted on: March 21, 2026
GSPD Blessing

Justice Center Blessing

Posted on: January 13, 2026
GSFR First Aid Courses

Gulf Shores Fire Rescue Offering Essential First Aid & CPR Courses

Posted on: January 9, 2026 | Last Modified on: January 23, 2026