We're closing out March with steady progress on the Waterway Village Pedestrian Bridge. Here is the latest update on construction activities for the week of March 27, 2026:
๐๐จ๐๐๐ฐ๐๐ฒ
Crews continued work on Waterway East Blvd this week, focusing on brick paver and sod construction. Looking toward next week, the initial binder layers of asphalt for East 2nd Street and the surrounding parking areas are scheduled to be laid on Monday, March 30.
๐๐ซ๐ข๐๐ ๐ ๐๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐๐ญ๐ข๐จ๐ง
The north side of the project is taking shape! The 1st vertical section of the North bridge columns is now complete. The 2nd vertical section is tentatively scheduled to be poured on Wednesday, April 1.
๐๐ฅ๐๐ฏ๐๐ญ๐จ๐ซ ๐๐จ๐ฐ๐๐ซ๐ฌ
Vertical progress continues on the elevator towers.
• North Tower: The second pour for the vertical walls is finished. The 3rd pour is currently scheduled for Saturday, March 28, or Monday, March 30.
• South Tower: Work is ongoing on the internal slabs and various structural components.
๐๐ซ๐๐๐๐ข๐ ๐๐ฉ๐๐๐ญ๐๐ฌ
East 2nd Street remains open to normal traffic operations. For those traveling north of the ICW, please remember that access is limited to local traffic only while Waterway East Blvd construction continues.
๐๐ฐ๐จ-๐๐๐๐ค ๐๐จ๐จ๐ค ๐๐ก๐๐๐
The Roadway and Concrete subcontractors expect to complete the current phase of Waterway East Blvd construction by next week. Over the next 4-6 weeks, the focus will remain heavily on the North Bridge Columns and North Elevator Tower walls.
As a reminder, the median curb on Waterway East Blvd and infrastructure near 25th Ave will be completed after the bridge structure is set in place.
Current Completion Date (Anticipated): January 8, 2027
Percent Time Used: 56.7%