Project Components
- New Third Southbound Lane from Coastal Gateway Boulevard to Fort Morgan Road (Hwy 180)
- Hwy 59 Access Management
- Intersection Improvements (L-Turn Lanes)
- New Entrance & Access Management at Publix
Project Phases:
Phase 1 (BUILD Grant) – Ft. Morgan Road to Cypress Bend Drive (Target)
Project will be managed by the City of Gulf Shores.
Timeline:
Construction Begins: Summer 2023
End Construction: Summer 2025
Phase 2 (ATRIP 2 Grant) – Cypress Bend Dr. (Target) to Coastal Gateway Blvd
Project will be managed by Alabama Department of Transportation (ALDOT).
Timeline:
Construction Begins: Fall 2023
End Construction: Fall 2025